Project Management
As developed in the 1950's by the U.S. Navy as a method to manage complex projects; the Program Evaluation and Review Technique (PERT) "is a network diagram that visually displays the activities and milestones which are required for project completion" (NETMBA.com. N.D. PP. 1). The assembling of a PERT chart requires the compilation of all tasks related to implementing and completing a project, developing activity times and their proper order, and identifying the critical path; the absolute necessity for effective project management.
In terms of creating a timeline, what is meant by the critical path of a PERT chart?
The critical path is "the sequence of schedule activities that determines the duration of the project" (Makar, A. September 10, 2009. PP. 1). Whether a project is outlined in days, weeks, or even years the critical path "identifies the total calendar time required for a project" (NETMBA.com. N.D. PP. 1). Arriving at the critical path begins with the calculation of each activity's duration and then subsequently identifying those which have zero slack or float time. "Slack is the amount of time a task can be delayed without impacting the start date of a subsequent task" (Makar, A. September 10, 2009. PP. 1). In essence the PERT chart's critical path highlights tasks which must...
Our semester plans gives you unlimited, unrestricted access to our entire library of resources —writing tools, guides, example essays, tutorials, class notes, and more.
Get Started Now